Update on River Rd Sidewalk and Pedestrian Bridge

river rd bridge

Work has begun on the pedestrian bridge over Falls River on River Rd. The foundations will be completed by the end of the month and the bridge will be installed in June. After the bridge is installed, we will complete the sidewalks, install the guardrail, and complete the final restorations of the site. If progress moves as planned, we expect the project to be completed by July 1.