|
Latest STEAP News
Courtesy of the Valley
Courier
By: Marianne Sullivan
ESSEX - Town officials are moving quickly to push forward with
plans to renovate the main streets of Essex Village and Ivoryton
Center. Just days after learning the town had received a $486,000
state grant for the project, planning meetings were underway.
First Selectman Philip Miller said last week that the town had
already put the engineering work out to bid with the request that
all bids be returned by Nov. 15.
"There is no resting on this project. We recognize this is
a very tight schedule, but we want to get the projects underway
and completed next spring. We hit the ground running," he said.
On Sept. 24 the State Bond Commission approved funding for the
town's proposal to upgrade and repair streets, sidewalks, and lighting
in its two main retail areas. The expectation is that the renovations
and upgrades will revitalize the look of both village centers and
encourage increased shopping from local residents and tourists.
The engineering work, Miller said, will involve design, layout,
and survey work along both main streets. He said that although the
timeframe given in the bid proposal was tight, he was encouraged
by the response he has received to date.
The town itself will serve as the general contractor for the project
and all subcontractors with winning bids will be required to submit
proof of insurance and product or work warranties. The town will
require a minimum of three bidders for all bid phases of the project.
If funds allow, the plans will include adding lights to Ferry Street
and extending a portion of the sidewalk at North Main Street.
Through the next few months, the small group working on the project
hope to select an engineer, have the completed engineering study
in hand, review it, present an overview to the Planning Commission,
and prepare bid packages for subcontractors. By mid-January, the
working group hopes to award bids to subcontractors.
By mid-March the town wants to begin the installation of curbs,
lighting standards, lighting wiring, and signage. A mild winter
and warmed temperatures by April will mean that sidewalks can be
poured and wiring competed. The town can also begin roadway demolition,
grading, drainage and paving.
If all goes well--according to this schedule--the project will
be completed in mid-April.
Along Main Street in Essex Village, the town will install approximately
4,000 feet of new granite curbing, which would be installed in conjunction
with the new paving of Main Street. In addition, approximately 16,000
square feet of new concrete sidewalks will be installed. Miller
said these would have a special brush finish and be scored to look
similar to paving blocks. Similar work will be done on Main Street
in Ivoryton Center. In addition, new street lighting will be installed.
The fixtures will be selected to reflect a period style.
|